You are here: Home » Solutions » 肯尼亚西部电网升级,我们如何用30台变压器保障关键节点可靠运行

肯尼亚西部电网升级,我们如何用30台变压器保障关键节点可靠运行

From 220kV Hub Substations to 33kV Terminal Distribution, ZiSheng Electrical Provides a Full-Chain Equipment Solution for KETRACO’s Kenya Project

This article documents how we addressed real-world challenges in Kenya’s power expansion project, including heat dissipation at high altitude, moisture protection near the lake environment, and coordinated delivery of multiple equipment models.

For Kenya’s power expansion project, we were awarded the contract to supply 30 transformers.

5子盛电气变压器生产制造工厂.jpg

The project owner is KETRACO, and the project is part of the Western Grid Upgrade EPC Project. The equipment scope includes:

  • 6 units of 150MVA transformers (220/66kV)

  • 14 units of 63MVA transformers (132/33kV)

  • 10 units of 30MVA transformers (33/11kV)

The equipment covers the entire chain from high-voltage transmission to terminal distribution.

This was not our first African project, but every project comes with its own challenges. For these 30 units in western Kenya, the main difficulties came down to three areas: environment, coordination, and delivery schedule.

I. High Altitude at 1,200 Meters: Challenges in Heat Dissipation Due to Thin Air

The project site is located at an altitude of approximately 1,200 meters, near Lake Victoria.

Anyone experienced in high-altitude projects understands that when air density decreases, two issues occur simultaneously:

  • The external insulation margin decreases.

  • Heat dissipation efficiency is reduced.

A transformer designed for standard low-altitude areas cannot simply be installed in such an environment without modifications; otherwise, long-term operation may face reliability risks.

Our approach was straightforward, but every step strictly followed engineering requirements:

  • Altitude correction was carried out according to IEC 60076 standards.
    We recalculated bushing creepage distances and air clearances to increase insulation safety margins.

  • Temperature rise was recalculated, and the cooling surface area was optimized.
    Instead of simply adding more radiators, we matched the cooling design based on the actual ambient temperature profile of the project location.

  • A fully sealed corrugated oil tank structure was adopted.
    This design was not simply to eliminate the conservator tank; more importantly, it reduces the exchange of external humid air with the transformer interior.
    Since the Kenya project site is close to Lake Victoria and experiences high humidity throughout the year, traditional designs with breathers carry a higher risk of moisture ingress during long-term operation.

Vacuum Oil Filling: A Manufacturing Step That Cannot Be Overlooked

There is one manufacturing process that is often underestimated: vacuum oil filling.

At our factory, all transformers underwent vacuum drying treatment followed by vacuum oil filling.

The objective was simple:

To reduce residual moisture inside the insulation materials to the lowest possible level.

For equipment operating in high-humidity environments, this process is often more critical than simply selecting a certain brand of insulation paper.

Enhanced Anti-Corrosion Protection for Lakeside Conditions

The corrosion protection system was designed to meet coastal environment standards:

  • Zinc-rich primer as the base layer

  • Epoxy intermediate coating

  • Polyurethane topcoat

The reason was not just because the specification required a higher protection level. In a previous East African project, we observed that conventional coatings developed rust spots after only three years in a lakeside environment.

4高湿热带环境变电站.jpg

II. Why It Is Better to Have One Supplier Handle Three Voltage Levels

This project involves three voltage levels: 220kV, 132kV, and 33kV. If three different suppliers were selected for each voltage level, technical interfaces, commissioning coordination, and future spare parts management would become significantly more complicated.

2输电—变电—配电三级电网结构图.jpg

Our solution was to supply all three voltage levels through Sheng Electrical, using:

  • A unified design system

  • A unified testing process

  • Unified technical standards

For the EPC contractor, this means:

  • Technical communication only needs to be handled with one team.

  • During installation and commissioning, equipment across different voltage levels follows consistent interface logic, reducing the risk of coordination issues.

  • During future operation and maintenance, the 14 units of 63MVA transformers and 10 units of 30MVA transformers can follow unified spare parts management and maintenance procedures, eliminating the need to maintain separate inventories for different manufacturers’ equipment.

This is not just a technical issue — it is a project management issue.

After more than 15 years of participating in EPC projects, we have gradually realized one thing:

EPC contractors are not most worried about expensive equipment; they are most concerned about delays caused by disputes and coordination problems between different suppliers.

III. For 30 Units of Equipment, How Do We Schedule Production Without Delays?

The project includes:

  • Three transformer capacities

  • Three voltage levels

  • A total of 30 units of equipment

The manufacturing cycles vary significantly among different models.

The six 150MVA transformers had the longest production cycle. Processes including core manufacturing, winding, assembly, and testing cannot be shortened excessively. After project kickoff, we prioritized these six units and aligned their key milestones with the civil construction and site handover schedule.

The 14 units of 63MVA transformers represented the largest quantity. However, their structure was relatively standardized, allowing us to adopt a modular production approach and maintain a stable manufacturing rhythm.

The 10 units of 30MVA distribution transformers featured a compact design and higher batch production efficiency. They were manufactured and shipped in batches according to the site installation schedule.

Early Procurement of Key Materials

Key materials were secured in advance.

Grain-oriented silicon steel and copper conductors account for a significant portion of transformer costs and are also among the materials most vulnerable to supply chain risks.

After project confirmation, we placed orders with steel mills and copper rod suppliers within the first week, bringing material preparation forward by nearly one month compared with normal production scheduling.

Complete Factory Testing According to IEC 60076 Standards

All factory tests were conducted in accordance with IEC 60076, including:

  • Transformer ratio test

  • DC resistance measurement of windings

  • No-load loss test

  • Load loss test

  • Insulation resistance test

  • Induced voltage withstand test

  • Lightning impulse test

  • Partial discharge test

For the 150MVA transformers, additional temperature rise tests were conducted according to project requirements.

All test data was fully archived and delivered together with the equipment to the project site.

Anyone with overseas project experience understands this:

Sometimes delivering complete documentation is even more important than delivering the equipment itself.

3电力变压器现场安装.jpg

IV. Beyond Equipment Supply, What Else Can We Provide?

When many customers first engage in overseas EPC projects, they often ask one question:

Besides manufacturing equipment, how far can a supplier support the project?

We usually divide our support into three stages:

4.1 Early-Stage Equipment Selection

When customers provide the single-line diagram, grid parameters, load requirements, and site environmental data, we review everything in detail with them, equipment by equipment.

How to match the voltage levels, how to select the transformer capacity, and how to optimize the design structure — all of these decisions need to be completed during the engineering design stage.

The more detailed the early-stage design is, the fewer problems will occur later.

4.2 Manufacturing Stage

A dedicated project team follows up throughout the manufacturing process, and key production milestones are photographed and documented.

If customers want to inspect the progress, they are welcome to visit our factory at any time. They can also appoint a third-party inspection company to conduct manufacturing supervision.

We have been implementing transparent production management for many years, and the process has become highly standardized and efficient.

4.3 Factory Delivery and Overseas Project Support

Technical documents are prepared according to project requirements, including:

  • Test reports

  • Technical specification sheets

  • Outline drawings

  • Installation manuals

  • Packing lists

  • Export documentation

For transportation, we can assist with coordination. During installation and commissioning, we provide technical guidance documents and professional support.

6压器出口交付.jpg

V. Final Thoughts

For us, the western Kenya project is more than just a single order.

It represents a typical African power grid upgrade project — with challenging environmental conditions, multiple voltage levels, and a tight delivery schedule. Successfully managing such a project demonstrates that our capabilities in design, manufacturing, project management, and export coordination are well integrated without major gaps.

When we first entered the transformer business 15 years ago, competition was mainly about price.

Today, the focus has shifted to more practical factors:

  • Can the equipment operate reliably after arriving at the project site?

  • Are the technical documents complete and accurate?

  • Can the supplier provide timely and effective support throughout the project?

These details may seem small, but they are often the factors that determine whether a project succeeds or fails.

If your project is located in Africa or other challenging environments and requires IEC-compliant power transformers, we welcome the opportunity to work with you.

We can get involved from the early solution design stage, helping you clarify:

  • Equipment selection

  • Technical specifications

  • Delivery schedules

Together, we can ensure that your project moves forward smoothly from planning to successful operation.

Personalized Customization Service

If the product does not meet your needs, please feel free to contact us at any time. We will provide you with exclusive and personalized services. 
We are willing to cooperate sincerely with clients all over the word with advanced technology, excellent quality, nice service, flexible operation and good reputation.
We are willing to cooperate sincerely with clients all over the world with advanced technology, excellent quality, nice service, flexible operation and good reputation.

Quick Links

Products

Resource

Contact Us

 Telephone: +86-191-3128-5373
WhatsApp: +8619131285373
 Email: info@bdzstransformer.com
 Address: No. 6799, North Third Ring Road, Jingxiu District, Baoding City, Hebei Province
Copyright © 2025 Baoding Zisheng Electrical Equipment Co., Ltd. All Rights Reserved.